Use this dialog box to set the acceleration options.
Schedule Cleanser
Field | Description |
Remove Redundant Logic
|
Select this option to lower the Redundancy Index to zero by removing unnecessary (redundant) links.
|
Remove Hard Constraints
|
Select this option to remove all hard constraints (MSO, MFO, Mandatory Start, Mandatory Finish) from the schedule.
|
Remove Soft Constraints
|
Select this option to remove all soft constraints (SNET, FNET, SNLT, FNLT, ALAP) from the schedule.
|
Remove Leads
|
Select this option to remove negative lags (leads) from the schedule. This results in a more realistic forecast.
|
Remove Lags
|
Select this option to eliminate the positive durations on relationships by removing the lags.
|
Convert Lags
|
Select this option to eliminate the positive durations on relationships by converting the lags to activities.
|
Links to Summaries
|
Select this option to eliminate the positive durations on relationships by converting the lags to activities.
|
Schedule Accelerator
Field | Description |
Accelerate Schedule Tab
|
- Use the
New Finish Date slider to manually set a new finish date and accelerate the duration.
- Select
Best Date Possible if you want Acumen to accelerate the date.
|
Accelerate Activity Tab
|
Use the options on this tab to accelerate a specific activity.
|
Select Acceleration Script
|
Select the script that you want to use for the acceleration.
|
Acceleration for 6 Month Update Scenario
This pane displays the effects of the acceleration based on the options you select in the above fields.